Application · Village microgrid
Where the grid arrives late or not at all, one 20–50 kW turbine on the village ridge can carry the school, the clinic, the water pump and a hundred households — for less than five years of diesel.
A village microgrid is a 400 V three-phase distribution line of 1–3 km, fed by one or two mid-size turbines, a PV array and a battery bank, with a diesel set for the calm month. A 50 kW turbine at a 5.5 m/s ridge site produces about 120 MWh a year — enough for 80–120 efficient households plus community loads.
The engineering is standard; the hard part is the tariff and the O&M. We supply the controller with prepaid-metering integration, train two local technicians, and stock the spare-parts kit that keeps the line up between site visits.
| Load | Power | Hours/day | Daily energy |
|---|---|---|---|
| Household connections (100 × 1 A) | 15,000 W | 6 h avg | 90 kWh |
| School and computer lab | 4,000 W | 8 h | 32 kWh |
| Clinic and vaccine fridge chain | 1,200 W | 24 h | 28.8 kWh |
| Village water pumping | 3,000 W | 4 h | 12 kWh |
| Cold store for produce | 2,500 W | 8 h | 20 kWh |
For mini-grids, two 20–50 kW machines on one surveyed ridge cost less per kWh than twenty 2 kW towers scattered along the road — fewer foundations, one crane mobilisation, one O&M route.
The hybrid controller runs wind and solar first, battery second, diesel only below 40 % state of charge. Prepaid meters keep household demand inside what the turbines actually produce.
Every mini-grid failure we have seen was a logistics failure, not an engineering one. Bearings, blades, controller boards and fuses stay on site; two trained locals handle 90 % of events the same day.
Send the site location and the load you need to power. You get a sized model, a price and a lead time — usually within one working day.